Guangdong Lianjiang Domestic Waste Incineration Power Plant is located in Qixingling Village, Hengshan Town, Lianjiang City, Guangdong Province, with a floor area of 150 mu (100,000 m²). The total design daily waste disposal capacity is 1,000 tons, the annual disposal of waste is about 330,000 tons, and the annual on-grid electricity is about 100 million kilowatt-hours.
The daily waste disposal capacity of the Phase I Project is 500 tons. The total investment amount of the Phase I Project is RMB 250 million, which is mainly used for the building of one 500 t/day reversed operated inclined reciprocating grate furnace and one 9MW condensing steam turbine generator set.
The supporting construction is to build flue gas cleaning system, leachate treatment system, fly ash and slag collection and treatment system, waste reception, storage and transportation system and other public and auxiliary facilities.
At present, it receives the domestic waste from 3 streets and 18 towns in Lianjiang City to realize the harmless, reduced and resourceful treatment of waste.